Disallowed cost
![]() |
Under cost reimbursable contracts, the contractor is paid actual costs – a calculation based on their accounts and records, rather than a pre-determined rate or price. However, not all costs can be accurately determined on a project-specific basis – some costs have only been incurred due to the contractor’s inefficiency, and not all costs are recoverable under the contract.
Options (C, D, E and F) of the New Engineering Contract (NEC) and Engineering and Construction Contract contract (EEC), describe the costs that can be recovered by the contractor as the ‘defined cost’, whereas the costs that cannot be recovered are described as the ‘disallowed cost’. The disallowed cost does not have to be paid by the employer and so is borne by the contractor. As a result, this is a common area of dispute.
Very broadly, the defined cost includes payments due to subcontractors and the cost of components for other works (such as plant, equipment and people), minus the disallowed cost.
The disallowed cost may include costs that appear to fall within the definition of defined cost, but that have been incurred as a result of the contractor’s failure or default.
This includes:
- Amounts that should not have been paid to a subcontractor.
- Amounts that are not justified by the contractor’s records.
- Resources that were not used.
- Costs incurred because the contractor did not follow the proper procedure.
- Failure to give early warning of anything that may delay the works, or increase costs.
- Defects corrected after completion.
- Preparation for adjudication.
Some defects corrected before completion are not disallowed. However, if a target cost (pain/gain) contract is being used, this will increase the defined cost, and so the potential ‘gain’ for the contractor is reduced, and the likelihood of ‘pain’ is increased. As a result, the contractor may in fact still end up paying for some of the costs of the defect.
The project manager decides whether a cost is disallowed. This must be done in accordance with the contract, and a reason must be given for each disallowed cost through the certification process.
[edit] Related articles on Designing Buildings Wiki:
- Atkins v Secretary of State for Transport.
- Alternative Dispute Resolution legislation.
- Compensation event.
- Contract conditions.
- Cost reimbursable contract.
- Defect.
- Defined cost.
- Delay damages.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Outturn cost.
- Period for reply.
- Target cost.
- Time Risk Allowance TRA.
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.